Electrics, plumbing, plastering, fitting an eastbourne kitchen

The kitchen has as expected taken up all of this week.
Oliver was off sick on Tuesday and so a delay started... by Thursday he and Abdul (his apprentice) had rewired the kitchen and corrected some horror scenarios in the consumer unit (fuse box). The best one being that when the main switch was turned off - the house was still live. Still all's well that ends well. The faults have been put right and the kitchen is now up to current regs. Oliver and Abdul finished 'first fix' on Wednesday. The owners then decided that they would like the kitchen walls skimmed prior to fitting the kitchen. This meant that Raf started plastering late on Wednesday evening and completed the task by just after 23:00.
By doing it like that Oliver was able to do 'second fix' and 'test and certify' by late Thursday afternoon. While all of this was happening I had sorted the rerouting of the plumbing so that it was all ready for the final connections when the kitchen was fitted... Friday morning we finally started fitting. By close of play today, Saturday, the clients now have a fully functioning kitchen. Monday will be a short day of small details and by the mid afternoon we will be on our way to the next job.

No comments: